Earned value analysis problems | Management homework help

 

 

 

General Instructions:

1.Submit your answers on a separate sheet of paper and submit through Blackboard

2Please show all the formulas used and step by step calculations

3.Draw Gantt Chart to calculate the Planned Value for the control points (for question # 2 and 3)

 

 

1.       a.     Find the schedule variance for a project that has an actual cost at month 22 of $540,000, a scheduled cost of $523,000, and an earned value of $535,000.

b. A project at month 5 had an actual cost of $34,000, a planned cost of $42,000, and value completed of $39,000. Find the schedule and cost variances.

c. A project at day 70 exhibits an actual cost of $78,000, a scheduled cost of $84,000, and a value completed of $81,000. Find the schedule and cost indices.

 

 

2.    Consider the information about a project plan in the following table.

Task

Immediate

Predecessor

Duration in Days

Scheduled

Cost/Day

A

4

$1,000

B

5

$2,000

C

A

4

$4,000

D

B

7

$1,000

E

C

6

$2,000

F

D

10

$3,000

 

 

The following table shows the weekly control reports for the first two weeks (assume 5 working days each week).

 

 

End of Week 1

End of Week 2

Task

Actual %

Completed

Cumulative

Actual Cost

Actual %

Completed

Cumulative

Actual Cost

A

50%

$1,500

100%

$ 2,900

B

30%

$3,000

100%

$11,000

C

10%

$2,000

100%

$13,500

D

10%

$2,000

90%

$10,000

E

0%

$        0

50%

$ 4,000

F

0%

$        0

0%

$        0

 

a. Use the earned value approach to calculate BCWP, BCWS, ACWP, SV, CV, SI, and CI for the whole project at Week1.

b. Calculate the cost variance and time variance for the project at the end of week 2.

c. Use the original estimate approach and the revised estimate approach to respectively estimate the final cost of this project at the end of week 1.

d. Use the original estimate approach and the revised estimate approach to respectively estimate the final cost of this project at the end of week 2.

 

 

3. A manufacturer of communication systems currently overhauls its computerized payroll system. Instead of using LOC (lines of code) to track the effort on devel­oping such a payroll system, the manufacturer adopts a more reliable method, function point analysis, for measuring/monitoring the progress of the project.

 

The new payroll system consists of eight modules, each with a certain amount of function points. From the manufacturer’s experience, each function point takes one week to develop. The ongoing project is evaluated at the end of the eighth week after its start.  The schedule/cost report is provided in the follow­ing table. (Assume linearity of cost vs. function point in each module.)

Comment on the status of the project at the end of week 8 based on the calculation of the project BCWP, BCWS, and ACWP. Is the project “in control”? if not, why not?

 

4.   Sandy Point is the project manager of a small project that consists of seven tasks. After careful and extensive planning, Sandy and her project staff agreed on a proposed project schedule that is indicated by the following Gantt chart:

As indicated in their original project plan, Sandy and her staff had estimated the following durations and (total) direct costs for each task:

 

Task

Duration (weeks)

Planned Value

A

4

$2800

B

7

$2800

C

3

$1150

D

5

$625

E

5

$1350

F

3

$1050

G

3

$270

This morning (beginning of week 6), Sandy received a progress report; as indicated in the Gantt chart, task C could not be started until this week due to the unexpected delay in completing task A. The report also indicates that task B has been completed two weeks earlier than expected. Information from the progress report is summarized in the following table.

a. As of today (beginning of week 6), what is the cost variance of the proj­ect?   What is the schedule variance of the project?

b. Based on information provided to date, what is your assessment of the cur­rent status of the project?







Place your order
(550 words)

Approximate price: $22

Calculate the price of your order

550 words
We'll send you the first draft for approval by September 11, 2018 at 10:52 AM
Total price:
$26
The price is based on these factors:
Academic level
Number of pages
Urgency
Basic features
  • Free title page and bibliography
  • Unlimited revisions
  • Plagiarism-free guarantee
  • Money-back guarantee
  • 24/7 support
On-demand options
  • Writer’s samples
  • Part-by-part delivery
  • Overnight delivery
  • Copies of used sources
  • Expert Proofreading
Paper format
  • 275 words per page
  • 12 pt Arial/Times New Roman
  • Double line spacing
  • Any citation style (APA, MLA, Chicago/Turabian, Harvard)

Our guarantees

Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.

Money-back guarantee

You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.

Read more

Zero-plagiarism guarantee

Each paper is composed from scratch, according to your instructions. It is then checked by our plagiarism-detection software. There is no gap where plagiarism could squeeze in.

Read more

Free-revision policy

Thanks to our free revisions, there is no way for you to be unsatisfied. We will work on your paper until you are completely happy with the result.

Read more

Privacy policy

Your email is safe, as we store it according to international data protection rules. Your bank details are secure, as we use only reliable payment systems.

Read more

Fair-cooperation guarantee

By sending us your money, you buy the service we provide. Check out our terms and conditions if you prefer business talks to be laid out in official language.

Read more

Get 15% OFF on your FIRST order. Use the coupon code: new15