Business finance – management week 2 assignment

Greyson Corporation Case Study

For use by University of Phoenix only. Copyright 2021 © John Wiley & Sons, Inc.

Greyson Corporation
Greyson Corporation was formed in 1970 by three scientists from the University of California. The major
purpose of the company was research and development for advanced military weaponry. Following World
War II, Greyson became a leader in the field of research and development. By the mid-1980s, Greyson
employed over 200 scientists and engineers.

The fact that Greyson handled only research and development (R&D) contracts was advantageous. First
of all, all of the scientists and engineers were dedicated to R&D activities; they did not have to share their
loyalties with production programs. Second, a strong functional organization was established. The project
management function was the responsibility of the functional manager whose department would perform
the majority of the work. Working relationships between departments were excellent.

By the late 1980s, Greyson was under new management. Almost all R&D programs called for
establishment of qualification and production planning. As a result, Greyson decided to enter into the
production of military weapons as well and capture some of the windfall profits of the production market.
This required a major reorganization from a functional to a matrix structure. Personnel problems occurred,
but none that proved a major catastrophe.

In 1994, Greyson entered into the aerospace market with the acquisition of a subcontract for the
propulsion unit of the Hercules missile. The contract was projected at $200 million over a five-year period,
with excellent possibilities for follow-on work. Between 1994 and 1998, Greyson developed a competent
technical staff composed mainly of young, untested college graduates. The majority of the original
employees who were still there were in managerial positions. Greyson never had any layoffs. In addition,
Greyson had excellent career development programs for almost all employees.

Between 1997 and 2001, the Department of Defense procurement for new weapons systems was on the
decline. Greyson relied heavily on their two major production programs, Hercules and Condor II, both of
which gave great promise for continued procurement. Greyson also had some 30hirty smaller R&D
contracts as well as two smaller production contracts for hand weapons.

Because R&D money was becoming scarce, Greyson’s management decided to phase out many of the
R&D activities and replace them with lucrative production contracts. Greyson believed that it could
compete with anyone in regard to low-cost production. Under this philosophy, the R&D community was
reduced to minimum levels necessary to support in-house activities. The director of engineering froze all
hiring except for job shoppers with special talents. All nonessential engineering personnel were
transferred to production units.

In 2002, Greyson entered into competition with Cameron Aerospace Corporation for development,
qualification, and testing of the Navy’s new Neptune missile. The competition was an eight-motor shoot-
off during the last 10 months of 2003. Cameron Corporation won the contract owing to technical merit.
Greyson Corporation, however, had gained valuable technical information in rocket motor development
and testing. The loss of the Neptune Program made it clear to Greyson’s management that aerospace
technology was changing too fast for Greyson to maintain a passive position. Even though funding was
limited, Greyson increased its technical staff and soon found great success in winning R&D contracts.

By 2005, Greyson had developed a solid aerospace business base. Profits had increased by 30 percent.
Greyson Corporation expanded from a company with 200 employees in 1994 to 1,800 employees in
2005. The Hercules Program, which began in 1994, was providing yearly follow-on contracts. All
indications projected a continuation of the Hercules Program through 2002.

Cameron Corporation, in contrast, had found 2005 a difficult year. The Neptune Program was the only
major contract that it maintained. The current production buy for the Neptune missile was scheduled for
completion in August 2005 with no follow-on work earlier than January 2006. Cameron Corporation
anticipated that overhead rates would increase sharply prior to next buy. The cost per motor would
increase from $55,000 to $75,000 for a January procurement, $85,000 for a March procurement, and

Greyson Corporation Case Study
Page 2 of 4

For use by University of Phoenix only. Copyright 2021 © John Wiley & Sons, Inc.

$125,000 for an August procurement. In February 2005, the Navy asked Greyson Corporation if it would
be interested in submitting a sole-source bid for production and qualification of the Neptune missile. The
Navy considered Cameron’s position uncertain and wanted to maintain a qualified vendor should
Cameron Corporation decide to get out of the aerospace business.

Greyson submitted a bid of $30 million for qualification and testing of 30 Neptune motors over a 30-month
period beginning in January 2006. Current testing of the Neptune missile indicated that the minimum
motor age life would extend through January 2009. This meant that production funds over the next
30 months could be diverted toward requalification of a new vendor, and production requirements for
2009 still could be met.

In August 2005, on delivery of the last Neptune rocket to the Navy, Cameron Corporation announced that
without an immediate production contract for Neptune follow-on work, it would close its doors and get out
of the aerospace business. Cameron invited Greyson Corporation to interview all of its key employees for
possible work on the Neptune Requalification Program. Greyson hired 35 of Cameron’s key people to
begin work in October 2005. The key people would be assigned to ongoing Greyson programs to become
familiar with Greyson methods. Greyson’s lower-level management was very unhappy about bringing in
these employees for fear that they would be placed in slots that could have resulted in promotions for
some of Greyson’s people. Management then decreed that these 35 people would work solely on the
Neptune Program, and other vacancies would be filled, as required, from the Hercules and Condor II
programs. Greyson estimated that the cost of employing these 35 people was approximately $150,000
per month, almost all of which was being absorbed through overhead. Without these 35 people, Greyson
did not believe that it would have won the contract as sole-source procurement. Other competitors could
have grabbed these key people and forced an open-bidding situation.

Because of the increased overhead rate, Greyson maintained a minimum staff to prepare for contract
negotiations and document preparation. To minimize costs, the directors of engineering and program
management gave the Neptune program office the authority to make decisions for departments and
divisions that were without representation in the program office. Top management had complete
confidence in the program office personnel because of their past performance on other programs and
years of experience.

In December 2005, the Department of Defense announced that spending was being curtailed sharply and
that funding limitations made it impossible to begin the qualification program before July 2006. To make
matters worse, consideration was being made for a compression of the requalification program to
25 motors in a 20-month period. However, long-lead funding for raw materials would be available.

After lengthy consideration, Greyson decided to maintain its current position and retain the 35 Cameron
employees by assigning them to in-house programs. The Neptune program office was still maintained for
preparations to support contract negotiations, rescheduling of activities for a shorter program, and long-
lead procurement.

In May 2006, contract negotiations began between the Navy and Greyson. At the beginning of contract
negotiations, the Navy stated the three key elements for negotiations:

1. Maximum funding was limited to the 2005 quote for a 30-motor/30-month program.

2. The amount of money available for the last six months of 2006 was limited to $3.7 million.

3. The contract would be cost plus incentive fee.

After three weeks of negotiations there appeared a stalemate. The Navy contended that the production
man-hours in the proposal were at the wrong level on the learning curves. It was further argued that
Greyson should be a lot “smarter” now because of the 35 Cameron employees and because of
experience learned during the 2001 shoot-off with Cameron Corporation during the initial stages of the
Neptune Program.

Since the negotiation teams could not agree, top-level management of the Navy and Greyson
Corporation met to iron out the differences. An agreement was finally reached on a figure of $28.5 million.
This was $1.5 million below Greyson’s original estimate to do the work. Management, however, felt that,
by tightening their belts, the work could be accomplished within budget.

Greyson Corporation Case Study
Page 3 of 4

For use by University of Phoenix only. Copyright 2021 © John Wiley & Sons, Inc.

The program began on July 1, 2006, with the distribution of the department budgets by the program
office. Almost all of the department managers were furious. Not only were the budgets below their original
estimates, but the 35 Cameron employees were earning salaries above the department mean salary, thus
reducing total man-hours even further. Almost all department managers asserted that cost overruns
would be the responsibility of the program office and not the individual departments.

By November 2006, Greyson was in trouble. The Neptune Program was on target for cost but 35 percent
behind for work completion. Department managers refused to take responsibility for certain tasks that
were usually considered to be joint department responsibilities. Poor communication between program
office and department managers provided additional discouragement. Department managers refused to
have their employees work on Sunday.

Even with all this, program management felt that catch-up was still possible. The 35 former Cameron
employees were performing commendable work equal to their counterparts on other programs.
Management considered that the potential cost overrun situation was not in the critical stage and that
more time should be permitted before considering corporate funding.

In December 2006, the Department of Defense announced that there would be no further buys of the
Hercules missile. This announcement was a severe blow to Greyson’s management. Not only was the
company in danger of having to lay off 500 employees, but overhead rates would rise considerably. There
was an indication last year that there would be no further buys, but management did not consider the
indications positive enough to require corporate strategy changes.

Although Greyson was not unionized, there was a possibility of a massive strike if Greyson career
employees were not given seniority over the 35 former Cameron employees in the case of layoffs.

By February 2007, the cost situation was clear:

1. The higher overhead rates threatened to increase total program costs by $1 million on the
Neptune Program.

2. Because the activities were behind schedule, the catch-up phases would have to be made in a
higher salary and overhead rate quarter, thus increasing total costs further.

3. Inventory costs were increasing. Items purchased during long-lead funding were approaching
shelf-life limits. Cost impact might be as high as $1 million.

The vice president and general manager considered the Neptune Program critical to the success and
survival of Greyson Corporation. The directors and division heads were ordered to take charge of the
program. The following options were considered:

1. Perform overtime work to get back on schedule.

2. Delay program activities in hopes that the Navy can come up with additional funding.

3. Review current material specifications in order to increase material shelf life, thus lowering
inventory and procurement costs.

4. Begin laying off noncritical employees.

5. Purchase additional tooling and equipment (at corporate expense) so that schedule
requirements could be met on target.

On March 1, 2007, Greyson gave merit salary increases to the key employees on all in-house programs.
At the same time, Greyson laid off 700 employees, some of whom were seasoned veterans. By March
15, Greyson employees formed a union and went out on strike.

Questions
1. What are the critical issues in the case?

2. How would you resolve each issue?

Greyson Corporation Case Study
Page 4 of 4

For use by University of Phoenix only. Copyright 2021 © John Wiley & Sons, Inc.

References

Kerzner, H. (2022). Project management case studies (6th ed.). John Wiley & Sons, Inc.







Place your order
(550 words)

Approximate price: $22

Calculate the price of your order

550 words
We'll send you the first draft for approval by September 11, 2018 at 10:52 AM
Total price:
$26
The price is based on these factors:
Academic level
Number of pages
Urgency
Basic features
  • Free title page and bibliography
  • Unlimited revisions
  • Plagiarism-free guarantee
  • Money-back guarantee
  • 24/7 support
On-demand options
  • Writer’s samples
  • Part-by-part delivery
  • Overnight delivery
  • Copies of used sources
  • Expert Proofreading
Paper format
  • 275 words per page
  • 12 pt Arial/Times New Roman
  • Double line spacing
  • Any citation style (APA, MLA, Chicago/Turabian, Harvard)

Our guarantees

Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.

Money-back guarantee

You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.

Read more

Zero-plagiarism guarantee

Each paper is composed from scratch, according to your instructions. It is then checked by our plagiarism-detection software. There is no gap where plagiarism could squeeze in.

Read more

Free-revision policy

Thanks to our free revisions, there is no way for you to be unsatisfied. We will work on your paper until you are completely happy with the result.

Read more

Privacy policy

Your email is safe, as we store it according to international data protection rules. Your bank details are secure, as we use only reliable payment systems.

Read more

Fair-cooperation guarantee

By sending us your money, you buy the service we provide. Check out our terms and conditions if you prefer business talks to be laid out in official language.

Read more

Get 15% OFF on your FIRST order. Use the coupon code: new15