1.The process of forecasting or approximating the time and cost of completing project deliverables is called
  A) Budgeting
  B) Predicting
  C) Estimating
  D) Planning
  E) Guesstimating
 
 
 

Janet is forecasting how much money her department needs to support a new project. She estimates that two people and $25,000 in expenses will cover her needs. Because management typically insists on reducing forecasts by 20 percent, she increases her estimates to allow for that reduction. Which of the following factors is illustrated in this situation?
  A) Padding estimates
  B) Planning horizon
  C) Project structure
  D) People
  E) Organization culture
 
 
 

Top-down estimates are most likely to occur during the ______ phase.
  A) Concept
  B) Planning
  C) Execution
  D) Delivery
  E) All of these are equally likely
 
 
 

Sean is forecasting the time and cost of developing a customized software program by looking at the number of inputs, outputs, inquires, files, and interfaces. Which of the following methods is he using?
  A) Ratio
  B) Template
  C) Apportion
  D) Function point
  E) Learning curve
 
 
 

Learning curves are more likely to apply in situations where most of the costs are
  A) Materials
  B) Labor
  C) Overhead
  D) Evenly spread over materials, labor, and overhead
  E) All of these are equally likely situations for learning curves
 
 
 

The approach that begins with a top-down estimate for the project and then refines estimates as the project is implemented is known as ______ method.
  A) Function point
  B) Template
  C) Learning curve
  D) Phase estimating
  E) Apportion
 
 
 

The accuracy of top-down estimates will typically be in the range of
  A) Minus 50% to plus 50%
  B) Minus 0% to plus 75%
  C) Minus 20% to plus 60%
  D) Minus 35% to plus 35%
  E) Minus 10% to plus 30%
 
 
 

The cost to prepare bottom-up estimates will typically run how much more than the costs to prepare the top-down estimates?
  A) About the same
  B) About twice as much
  C) About three times as much
  D) About four times as much
  E) About five times as much
 
 
 

Project costs are typically viewed from all of the following except:
  A) Scheduled
  B) Sunk
  C) Actual
  D) Committed
  E) All of these are correct
 
 
 
10 
Which of the following is not one of the recommended guidelines for developing useful work package estimates?
  A) Estimates should be made by those responsible for the work
  B) Use several people to estimate the same work
  C) Estimates should be based on normal conditions
  D) Estimates should include a normal level of contingency
  E) Estimates should be independent of other projects
 
 
 
11 
Reasons why estimating time and cost are important include all of the following except:
  A) To schedule work
  B) To determine how long the project should take and cost
  C) To develop cash flow needs
  D) To determine how well the project is progressing
  E) All of the above are valid reasons
 
 
 
12 
The bottom-up approach for estimating times and costs that uses costs from past projects that were similar to the current project is known as:
  A) Detailed WBS work package estimates
  B) Template method
  C) Function point method
  D) Time-phased cost estimates
  E) Phase estimating
 
 
 
13 
Which of the following top-down methods is used when projects closely follow past projects in features and costs and result in costs being assigned by percentages to major segments of the project?
  A) Apportion
  B) Function point
  C) Phase estimating
  D) Learning curve
  E) Consensus
 
 
 
14 
People working on prototype development needing time to interact with the design engineers after the design is completed is an example of:
  A) Hidden interaction costs
  B) Things going wrong on a project
  C) Normal conditions not applying
  D) Changes in project scope
  E) None of these are correct
 
 
 
15 
Design flaws being revealed after the fact, extreme weather conditions, and accidents occurring are examples of:
  A) Hidden interaction costs
  B) Things going wrong on a project
  C) Normal conditions not applying
  D) Changes in project scope
  E) None of these are correct
 
 







Place your order
(550 words)

Approximate price: $22

Calculate the price of your order

550 words
We'll send you the first draft for approval by September 11, 2018 at 10:52 AM
Total price:
$26
The price is based on these factors:
Academic level
Number of pages
Urgency
Basic features
  • Free title page and bibliography
  • Unlimited revisions
  • Plagiarism-free guarantee
  • Money-back guarantee
  • 24/7 support
On-demand options
  • Writer’s samples
  • Part-by-part delivery
  • Overnight delivery
  • Copies of used sources
  • Expert Proofreading
Paper format
  • 275 words per page
  • 12 pt Arial/Times New Roman
  • Double line spacing
  • Any citation style (APA, MLA, Chicago/Turabian, Harvard)

Our guarantees

Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.

Money-back guarantee

You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.

Read more

Zero-plagiarism guarantee

Each paper is composed from scratch, according to your instructions. It is then checked by our plagiarism-detection software. There is no gap where plagiarism could squeeze in.

Read more

Free-revision policy

Thanks to our free revisions, there is no way for you to be unsatisfied. We will work on your paper until you are completely happy with the result.

Read more

Privacy policy

Your email is safe, as we store it according to international data protection rules. Your bank details are secure, as we use only reliable payment systems.

Read more

Fair-cooperation guarantee

By sending us your money, you buy the service we provide. Check out our terms and conditions if you prefer business talks to be laid out in official language.

Read more

Get 15% OFF on your FIRST order. Use the coupon code: new15